Coastal Panhandle Project Schedule

Bay County
Preliminary Flood Study Products September, 30, 2017*
Preliminary DFIRM Community Coordination Meeting To be scheduled: September 2017 January 2018
Flood Risk Open House To be scheduled: September 2017 January 2018
Appeal Period Planned to occur between: January 2018 June 2018
Start of 6-Month Compliance Period (Issue Letter of Final Determination) Summer 2018 (June August)
Effective Flood Study Products Early 2019 (February April)
Escambia County
Preliminary Flood Study Products January 27, 2017*
Preliminary DFIRM Community Coordination Meeting To be scheduled: February 2017 March 2017
Flood Risk Open House To be scheduled: February 2017 March 2017
Appeal Period Planned to occur between: April 2017 September 2017
6-Month Compliance Period (Issue Letter of Final Determination) Winter 2017 (October December)
Effective Flood Study Products Spring 2018 (April June)
Gulf County
Preliminary Flood Study Products May 2, 2016
Preliminary DFIRM Community Coordination Meeting August 9, 2016*
Flood Risk Open House August 9, 2016*
Appeal Period Planned to occur between: April 2017 September 2017
Start of 6-Month Compliance Period (Issue Letter of Final Determination) Fall 2017 (October December)
Effective Flood Study Products Spring 2018 (April June)
Okaloosa County
Preliminary Flood Study Products April 29, 2016
Preliminary DFIRM Community Coordination Meeting June 28, 2016
Flood Risk Open House June 28, 2016 and June 29, 2016
Appeal Period February 22, 2017 May 23, 2017
Start of 6-Month Compliance Period (Issue Letter of Final Determination) Summer 2017 (June August)
Effective Flood Study Products Winter 2017 2018 (December March)
Santa Rosa County
Preliminary Flood Study Products July 18, 2016
Preliminary DFIRM Community Coordination Meeting September 28, 2016
Flood Risk Open House September 28, 2016 and September 29, 2016
Appeal Period Planned to occur between: February 2017 July 2017
Start of 6-Month Compliance Period (Issue Letter of Final Determination) Fall 2017 (August October)
Effective Flood Study Products Early 2018 (February April)
Walton County
Preliminary Flood Study Products March 16, 2016
Preliminary DFIRM Community Coordination Meeting June 7, 2016
Flood Risk Open House June 7, 2016 and June 8, 2016
Appeal Period November 17, 2016 February 15, 2017
Start of 6-Month Compliance Period (Issue Letter of Final Determination) Early 2017 (February March)
Effective Flood Study Products Fall 2017 (August October)

*Dates are planned and may be subject to change. Please revisit for future schedule updates.